Centrifugally Cast Concrete Relining

Rio Tinto Culvert Refurbishment Program Phase 4

Refurbishing 14 culverts with the cumulative length of 160 m is no small feat. Using innovative technology, Aaro was able to streamline these works to provide the clients with increased value.

BGC Contracting needed to refurbish five different culvert locations along with Rio Tinto’s rail network. And, they needed experts to help them do it. The team at Aaro were the perfect fit. 

The entire refurbishment involved a total of 14 culverts, ranging in diameter from 1200mm to 3100mm with a cumulative length of approximately 160m. The differing culvert diameters complicated the task for our team — but Aaro found a solution.

The culverts were refurbished using CentriPipe, a Centrifugally Cast Concrete. Centripipe is a cementitious material that performs structurally similar to a non-reinforced concrete pipe.

$950k

Client

BCG Contracting

Location

Pilbara, WA

Project Duration

4 Months

Project Start

July 2016

Project Finish

October 2016

RelatedProjects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

$1m50 Year Design Life on 5.75m Tunnel RefurbishmentCentrifugally Cast Concrete Relining
We were asked to structurally reline a 5.75m diameter multi-plate culvert and were able to provide the client a cost saving alternative and still achieved the 50 year design life requirement.
Pilbara, WA

Our experts can make your next project a success.

Discover how Aaro could provide you with expert solutions backed by experience.

Get in touch
One group, many services