Aaro Projects

Newdegate WWTP Redirect Inlet Sewer Line

Read More Carrot icon
graphic graphic

Details

Description

Aaro was awarded the contract for the Newdegate Wastewater Treatment Plant (WWTP) Inlet Sewer Line Redirection by Water Corporation.

Water Corporation required a contractor to manage the complete manufacture, supply, construction, testing, and commissioning of new wastewater conveyance and treatment infrastructure assets.

List of Project Services:

  • Intercepted the existing incoming sewer line and redirected to the southeast corner of the primary pond
  • Constructed new manholes and installed bypass sewer pipework
  • Installed a baffle curtain in the primary pond to optimise treatment flow
  • Optimised the plant’s hydraulic profile between the new inlet manhole
  • and existing systems
  • Adjusted inlet and outlet pipework levels as required
  • Installed isolation stopboards in new junction manholes to enable future use of bypass pipework
  • Decommissioned the existing inlet sewer and rehabilitated earthworks within the WWTP boundary fence
  • Removed and disposed of stored sludge, geobags, bunded liner, and sandbags at an approved landfill

Aaro’s dedicated project managers and site supervisors ensured a high level of customer service and professionalism throughout each phase of the project, adhering to Water Corporation’s quality and safety standards at every step.

Summary

$316k

Total Net Volume

Client
Water Corporation
Location
Newdegate
Project Duration
2 Months
Project Start
April 2024
Project Finish
June 2024

Gallery

>
Featured Modal Image

Talk to our Construction Experts

We support our clients when they need it most. Contact our experts to see how Aaro can partner with your business.

Leave a Reply

Your email address will not be published. Required fields are marked *