Details
Description
Aaro was awarded the contract for the Newdegate Wastewater Treatment Plant (WWTP) Inlet Sewer Line Redirection by Water Corporation.
Water Corporation required a contractor to manage the complete manufacture, supply, construction, testing, and commissioning of new wastewater conveyance and treatment infrastructure assets.
List of Project Services:
- Intercepted the existing incoming sewer line and redirected to the southeast corner of the primary pond
- Constructed new manholes and installed bypass sewer pipework
- Installed a baffle curtain in the primary pond to optimise treatment flow
- Optimised the plant’s hydraulic profile between the new inlet manhole
- and existing systems
- Adjusted inlet and outlet pipework levels as required
- Installed isolation stopboards in new junction manholes to enable future use of bypass pipework
- Decommissioned the existing inlet sewer and rehabilitated earthworks within the WWTP boundary fence
- Removed and disposed of stored sludge, geobags, bunded liner, and sandbags at an approved landfill
Aaro’s dedicated project managers and site supervisors ensured a high level of customer service and professionalism throughout each phase of the project, adhering to Water Corporation’s quality and safety standards at every step.
Summary
$316k
Total Net Volume
Client
Water Corporation
Location
Newdegate
Project Duration
2 Months
Project Start
April 2024
Project Finish
June 2024