Dampier Potable Water Upgrade – Installation of Replacement Potable Water Line

Read More Carrot icon
graphic graphic

Details

Description

Aaro Group was engaged by Rio Tinto to replace the Peninsula Palms supply mains.

The project involved:

  • Clearing vegetation along the easement and reinstating grassed areas as needed.
  • Coordinating with RTIO Utilities for pipeline isolation and draining.
  • Excavating trenches per AS-0130-P-00011specifications, including under two driveways.
  • Removing the existing DN150 MSCL watermain and installing 250 meters of DN150 PN20 PVC Blue Brute pipe with necessary fittings.
  • Completing two tie-ins to the existing pipeline at Peninsula Palms and the southern end near Tin City.
  • Conducting commissioning activities, including flushing, hydrostatic testing at 900 KPa, and disinfection, with chlorinated water disposed of at Dampier WWTP.

This project highlights Aaro Group’s dedication to quality and safety in infrastructure work.

Summary

$382k

Total Net Volume

Client
RIO Tinto
Location
Dampier
Project Duration
3 Months
Project Start
August 2024
Project Finish
November 2024

Gallery

>
Featured Modal Image

Talk to our Construction Experts

We support our clients when they need it most. Contact our experts to see how Aaro can partner with your business.

Leave a Reply

Your email address will not be published. Required fields are marked *