Aaro Projects

DSL Paradise Creek PS Culvert UV CIPP

Read More Carrot icon
graphic graphic

Details

Description

Aaro was awarded the contract by Cowans Plumbing to deliver a critical culvert rehabilitation project utilising state of the art UV CIPP technology. The project was designed to rehabilitate a deteriorating culvert, ensuring long-term durability and reduced maintenance costs.

Scope of Works

  • Mobilisation and demobilisation of personnel, equipment, and materials.
  • Supply and precise installation of two UV CIPP liners, 1030mm in diameter and 24m in length, with a thickness of 7.9mm.
  • Curing of liners to specified standards to achieve durability and functionality.

The UV CIPP liners were installed successfully, enhancing the culvert’s performance and lifespan. The project met all quality and timeline requirements, reflecting Aaro’s commitment to efficient and innovative infrastructure solutions.

Summary

$225k

Total Net Volume

Client
Cowans Plumbing Services
Location
Port Headland
Project Duration
4 Months
Project Start
May 2024
Project Finish
September 2024

Gallery

>
Featured Modal Image

Talk to our Construction Experts

We support our clients when they need it most. Contact our experts to see how Aaro can partner with your business.

Leave a Reply

Your email address will not be published. Required fields are marked *